- Completed
- PSPP-FI-GEARBOX-NLT
Independent Inspection and No-Load Testing of Heavy-Duty Industrial Gear Units
A large industrial project required verification of heavy-duty gear units intended for a mechanical drive package. At the manufacturing stage, independent inspection was needed to assess equipment condition, key dimensions, surface protection and operating behavior before the units progressed toward final acceptance and shipment. The inspection visit covered one gear unit undergoing a no-load test, another finished unit available for dimensional and coating checks, and additional units still in assembly.

- 1,286 rpm
- Rated input speed
- 165 min
- Test duration
- None
- Open nonconformities
- Two
- Open punch-list items
Scope & Approach
Project at a glance
- Equipment
- Heavy-duty industrial gear units, including right- and left-hand drive configurations
- Sector
- Oil & gas / industrial material handling
- Inspection location
- Manufacturing facility in Finland
- Inspection activities
- Material review; visual and dimensional verification; no-load running test; coating thickness assessment
- Reported outcome
- Satisfactory with comments; two open punch-list items; no release note issued
The inspection challenge
The equipment was at different stages of manufacture, making it necessary to verify different characteristics on different units. Certain dimensions were inaccessible on the completed unit because covers and couplings were installed. The inspector therefore used the unit on the test bench and partially assembled units for complementary dimensional checks. The assignment also required clear separation between witnessed testing and activities that the manufacturer had completed before the visit.

Scope of inspection
Review of available inspection and test plan, drawings, inspection certificates and test documentation.
Visual inspection of gearbox housings, shaft seals and accessible assemblies.
Dimensional verification against the general arrangement drawing, including input/output shaft geometry.
Witnessing of no-load clockwise and counter-clockwise operation, including an overspeed stage.
Monitoring of operating speed, bearing temperatures, vibration and noise.
Dry-film thickness (DFT) assessment of the painted unit and review of surface condition.
Recording deviations and outstanding actions requiring clarification before final release.
Testing and technical verification
The witnessed no-load test included one hour in each direction at a rated input speed of 1,286 rpm, followed by an overspeed stage at 110% of rated speed. The report records a total running time of 165 minutes. The observed noise and vibration were assessed as acceptable, and no abnormal operating behavior or oil leakage at the shaft seals was reported.
- Rated input speed
- 1,286 rpm
- Test duration
- 165 minutes total
- Gear ratio
- 83.70
- HSS bearing temperature
- 44 °C
- LSS bearing temperature
- 31 °C
- Recorded sound level
- 72.5–73.7 dB(A)
- Test conclusion
- Operating parameters reported acceptable
The dimensional checks were reported satisfactory. The inspected coating thickness was satisfactory, and the accessible shaft seal areas showed no leakage during the witnessed run.

Findings and actions
The visit concluded “satisfactory with comments,” with no open nonconformities recorded. Two punch-list items remained open:
- 01
Rated power discrepancy: the order/notification indicated 315 kW, while other values were discussed during the inspection. Confirmation against the applicable technical data sheet was required.
- 02
Speed measurement calibration documentation: one of five recorded calibration values was outside the stated range; the discrepancy was referred for client information and possible supplier clarification.
Additional completion points included applying equipment tag numbers and verifying the final identification at a later inspection. The report notes that the air leak test and oil filling had already been performed by the manufacturer and were not witnessed; the oil level itself was not independently checked. Backstop components located at another facility were outside this visit’s inspection scope.
Project outcome
The inspection provided documented evidence of acceptable witnessed no-load performance, dimensional condition and coating assessment for the sampled units. It also surfaced technical and documentary questions early enough to be addressed through the project’s inspection and acceptance process. The report did not authorize final shipment: two punch-list items remained open and no release note was issued.
Why independent inspection matters
For industrial drive packages, even a small mismatch between equipment ratings, test records and purchase specifications can create uncertainty at installation or commissioning. Independent witness inspection gives project stakeholders a clearer view of equipment readiness, distinguishes directly observed results from manufacturer statements, and preserves a traceable list of unresolved items before release.
3BPSPP d.o.o. inspection capability
3BPSPP d.o.o. supports industrial projects through vendor inspection, manufacturing surveillance, mechanical testing witness, expediting and QA/QC documentation review. Our approach emphasizes independent reporting, practical verification against approved project requirements and prompt communication of deviations.
Independent inspection. Clear findings. Better project decisions.
Related work
More case studies

Third-Party Inspection & Manufacturing Expediting of SAWL Mother Pipes for Offshore Subsea Pipelines
3BPSPP tehnične dejavnosti d.o.o. carried out third-party inspection, manufacturing surveillance, and expediting activities for the production of carbon steel Submerged Arc Welded Longitudinal (SAWL) mother pipes intended for hot induction bends used in an offshore subsea pipeline project.
- Status
- Completed
- Region
- Germany

Middle Eastern Onshore LNG Slug Catcher — Clad Pipe Inspection & Expediting
Inspection and expediting of CRA clad pipe (Alloy 625) for a major Middle Eastern onshore LNG slug catcher project — radiographic review, MUT/MPI, defect mapping and EN 10204 3.2 Manufacturing Data Book alignment.
- Status
- Active
- Region
- Qatar

East African LNG Onshore Pipeline — SAWL Line Pipe Inspection
Third-party inspection and expediting of SAWL line-pipe production for an East African LNG onshore pipeline — from plate through forming, tack welding and SAW to weldability testing and 100% NDT.
- Status
- Completed
- Region
- Republic of Mozambique